63rd St. Station, Second Ave. Subway Line Shoring
Temporary shoring at the second floor of approximately ninety feet of exterior bearing wall and storefront of a depression era six-story fully occupied apartment building. Read more at: https://www.structuremag.org/?p=7810
Bronx Plaza Structure Rehabilitation at the RKF Bridge
Complete temporary shoring design for all aspects of this bridge rehabilitation for this TBTA project
Bronx River Greenway Pedestrian Bridge Over The Bronx River
Complete construction procedure design providing temporary shoring in the Bronx River for the NYC DDC Project.
Eastern Parkway Brooklyn Museum Subway Station Excavation
Support of excavation design for the installation of three (3) elevators for the NYCTA at the Brooklyn Museum.
George Washington Bridge Rehabilitation of the 178th and 179th Street Ramps
Temporary shoring of ramps for fascia stringer replacements including bearing replacements, support of excavation and deck reconstruction design
Henry Hudson Bridge-Replacement of Lower Level Deck and Upper Level Curb Stringers
Temporary shoring for bearing replacements, gantry crane design, demolition and reconstruction design associated with the rehabilitation associated with these TBTA projects
Installation of East Side Coastal Resiliency
Temporary pedestrian bridge and ramps over the F.D.R.
NYCTA A-370150E – Accessibility Upgrades at the 149th Street Grand Concourse Complex on the Jerome Avenue/White Plains Road Lines
Reconstruction and Rehabilitation of the Upper-Level Approach Decks at the Verrazano-Narrows Bridge
Staten Island Approach Temporary Shoring for Pier Replacement
Reconstruction of the Upper and Lower Levels Toll Plazas and Southbound Approach at the Henry Hudson Bridge
400 ton compression and 160 ton tension test design for micro-piles at this TBTA project
Rehabilitation of 6 Bridges at Various Locations over the Sprain Brook Parkway
Temporary Shoring design for complete pier replacement for this NYS DOT Project.
Rehabilitation of Riverside Drive Viaduct Over 158th Street
400 ton temporary lifting frame design for bearing replacements of large cantilevered floor beams over Amtrak railroad for this City of New York DOT Project.
Van Wyck Expressway Viaduct Rehabilitation
Temporary shoring design for complete pier replacement for this NYS DOT Project.